Thorough renovation and expansion on a design and build formula of two popular outlet centres in line with the BREEAM ‘Very Good’ quality label. We also built the new reception building in Roermond.
Neumünster: 04/2019 - 07/2020
Roermond: 06/2019 - 02/2021
Â
location
Project Details
Contractor
Oderstraße 10, Neumünster, Schleswig-Holstein, Germany
Stadsweide 2, TD Roermond, Netherlands
Client
McArthurGlen
Price
€17.000.000
Architects
Kern architecten (Roermond)
Petersen + Hutchinson Architekten (Neumünster)
Special features
Construction period
1 year 10 months
Start work
04-2019
End of work
02-2021